When can a development appeal be made?                

 

A development appeal to the Court under s 97 or s 97AA is generally to be made within 6 months after:

  • the date on which the applicant received notice of the determination of the application or review, or

  • the date on which that application is taken to have been determined (see s 97(1) and s 97AA(1) of the Planning Act).

A development application is taken to have been determined (that is, it is deemed to have been refused) if:

  • the development application was lodged with the consent authority

  • a certain period of time has elapsed, and

  • there has been no determination.

For appeals concerning development applications under s 97 of the Planning Act, an application is deemed to have been refused (in s 82(1) of the Planning Act and cl 113 of the Planning Regulations) after:

  • 40 days for ordinary development

  • 60 days for designated development or integrated development

  • 90 days for State significant development.

For appeals concerning modification of development consents under s 97AA of the Planning Act, the deemed refusal period is generally 40 days after the application was made (according to s 96(6) and 96AA(3) of the Planning Act and cl 122 of the Planning Regulations).

When can an objector appeal be made?

An objector appeal under s 98 of the Planning Act is to be made within 28 days after the date on which notice of the determination was given (see s 98(1) of the Planning Act).

 

 